Umm Qasr Power Plant 29.3 MW
Scope of Work The Umm Qasr Power Plant (“UQPP”) project consists of the design, procurement, construction, and commissioning of a 29.34MW (Phase 1) gas fired captive power plant located at Umm Qasr Port, Basra Governorate, Republic of Iraq. The purpose of this plant is the deliver baseload 24/7 power to the Umm Qasr operated by…
-
Sharjah Waste to Energy Project
Scope of Work Civil works of the entire site and the construction of all buildings of the project which consist of 30MW generation from the Sharjah Municipality domestic waste and tie-in to SEWA’s grid. Project Description Masdar and Bee’ah, are developing a cutting-edge waste-to-energy plant in Sharjah, the Middle East’s leading and award-winning environmental management…
-
Air Separation Unit Civil Construction, Mechanical and Electrical Erection
Scope of Work Civil construction including piling Foundations and steel structure buildings, Mechanical and Electrical Erection Works for the ASU Package (Construction of an Air Separation Unit Plant for that separates atmospheric air into its primary components: Nitrogen, Oxygen and Argon) Project Description Civil works: Piling and civil works for foundations for buildings Process equipment’s…
-
Upgrade Fire Protection and Industrial Drainage System Turaif
Scope of Work To upgrade the existing Storm Water Drainage and Firewater Distribution systems. The purpose of the facility is to restore and upgrade the firefighting capability and industrial drainage systems to meet safety requirements. BUTEC is responsible of material procurement, construction management, quality management, and testing and commissioning of all works related to the…
-
Deira Island Wastewater Treatment Plant
Scope of Work EPC of the Sewage Treatment Plant including incoming sewer pipes, inlet sewage lift station, inlet headworks, Biological treatment and associated works (Electrical substation MV, LV) as well as testing and commissioning of the STP. Project Description Population equivalent: 240,000 PE • Total daily design flow: 36,000 m3/d Design peak flow: 3,000 m3/h…
-
Distribution Network with Customer and Metering Services
Scope of Work Network survey Assessing the condition of all assets Developing network mapping Network inventory Plans & programs Developing procedures for each of the activities to be performed in the execution of the contact Developing an investment plan to improve the state of the network based on the survey findings Planning & design Revision…
-
Qatar Foundation QSTP Tech 4 Buildings
Scope of Work EPC, coordination, development, installation, testing and commissioning of the Tech 4 facility with internal mezzanine floors, workshops and offices. The scope also involves infrastructure development works within the plot limit, such as roads, parking, paved areas, landscape works, signage, etc. Project Description The Tech 4 building worksite is located in Zone 4…
-
Bellara Steel Complex Balance of Plant
Scope of Work Construction of all utilities buildings, foundation works for technological packages, piping and cabling interconnection between technological packages, roads, and infrastructure surrounding the different process facilities of the steel factory Project Description Foundation works for the technological packages in the BELLARA project such as piling works (872 piles) and concrete foundations (45,000…