Shah Gas Development Program Buildings Works Package B
Employer
Al Hosn Gas, Abu Dhabi
Role of BUTEC
Awarded
Completed
Scope of Work
EPC in addition to testing and commissioning for all civil works, as well as associated MEP works and equipment installation. It covers 12 buildings of package “B” related to the units Shah Process Plant (EPC package 2) & Shah Sulfur Recovery Units (EPC package 3), located at Shah, U.A.E. in the frame of the Shah Gas Development (SGD) Program.
Scope of work includes also the construction of a site camp covering an area of 70,000 m2 for 700 residents (housing canteen, nursery, recreation areas and sport fields, etc.).
Project Description
Package 2:
- Central area: 3 primary substations 33/11 kV
- West area: 2 primary substations 33/11 kV
- East area: 3 IES (instrument equipment shelters)
Package 3:
- Central area: 3 primary substations 33/11 kV and 1 IES (instrument equipment shelter)