2x4MW Battery Energy Storage System
Employer
ADWEA (Abu Dhabi Water & Electricity Authority)
Role of BUTEC
Awarded
Completed
Scope of Work
EPC including the following:
- New BESS buildings complete with MEP works
- Trenching & cabling between main substation & BESS building
- Integration of BESS and associated systems
- Lightning protection and earthing
- 2 auxiliary transformers, dry type, 11/0.41 kV, 1,500 kVA
Project Description
2 units (concrete and steel pre-engineered buildings), 4 MW each, at the following substations:
- HTCO 132/11 kV primary grid substation (E25)
- Port 132/11 kV primary grid substation (E14)