Power Transmission System Expansion P VIII Umm Birka S/S

Employer

KAHRAMAA (Qatar General Electricity & Water Corporation)

Role of BUTEC

Subcontractor for civil and MEP works Main contractor: Areva T&D S.A

Awarded

October 2008

Completed

January 2010

Scope of Work

EPC, site delivery, testing & commissioning of all civil works, including all associated MEP works and equipment installation for 400/220/132/11 kV GIS substations:

  • Mechanical: Plumbing, HVAC, and fire fighting.
  • Electrical: Internal/external lighting, small power, distribution boards, telephone network system, intrusion alarm, fire detection and alarm, earthing and lightning.
  • Architectural and finishing works for the construction of all GIS buildings.
  • Infrastructure, site works and landscaping.