Restoration of Casino Bridge
Employer
Council for Development and Reconstruction (CDR) Casino du Liban
Role of BUTEC
Awarded
Completed
Project Description
- Arch bridge – clear span 95 m
- Project restoration consisted of:
- Demolition & reconstruction of almost 120 m of damaged arches with associated deck slab
- Utilization of prestressed strand for stress relief on remaining structure (300 tons) & jacking (400 tons) at key end after reconstruction
- Use of suspended platform over variable heights
- High strength concrete application (600 kg/cm2)